Prepare for your Non-conformance Management interview with these questions covering identification, documentation, resolution, and prevention of issues. Click on questions to view detailed answers.
"The delivered concrete has a slump value that is too high (it's too wet) compared to what was specified in the project plan. This means it doesn't meet the required workability standard."
This non-conformance needs to be addressed before the concrete is used, as it could affect the final strength and durability of the structure.Correction: This is an action taken to fix the immediate non-conformance or problem. It deals with the symptom.
Corrective Action: This is an action taken to eliminate the cause of a non-conformance and prevent it from happening again. It deals with the root cause.
Impact on Project Quality:
Impact on Project Cost:
Challenges:
Addressing Challenges: