Download PDF
Send Feedback
Home

Roof Beam & Tie Beam Quality Check Procedure

Standard operating procedure for quality control of Plinth, Roof Beams & Tie Beams, ensuring structural stability, durability, and load-bearing capacity through proper inspection and testing methods in accordance with Indian Standards (IS Codes).

Structure Type: RCC Beams Quality Priority: High Validity: All Projects
1

Objective

To establish a comprehensive quality control procedure for Plinth, Roof Beams & Tie Beams, ensuring structural stability, durability, and load-bearing capacity through proper inspection and testing methods in accordance with Indian Standards (IS Codes).

2

IS Code References

Inspection Stage IS Code Description
Excavation & Foundation IS 1200:1974, IS 6403:1981 Earthwork Measurement & Soil Bearing Capacity
Formwork & Alignment IS 14687:1999 Guidelines for Falsework
Reinforcement Check IS 456:2000, IS 2502:1963 Concrete & Rebar Detailing
Concrete Mix Design IS 10262:2019, IS 383:2016 Mix Design & Aggregate Quality
Concrete Pouring & Vibrations IS 1199:1959, IS 4925:2004 Slump Test & Batching
Concrete Strength Testing IS 516:1959 Cube Test for Strength
Final QA/QC Checks IS 456:2000 Tolerances & Quality Control
3

Pre-Casting / Pre-Pouring Inspection

A
Formwork & Alignment Check
  • Ensure formwork dimensions match the structural drawing
  • Formwork should be properly supported and braced to avoid deformation (IS 14687:1999)
  • Ensure formwork is clean, oiled, and has no gaps to prevent leakage
  • Verify that formwork can withstand pouring pressure without displacement
  • Check formwork joints are tight and properly sealed
  • Verify proper centering and support system for beam soffit
IS 14687:1999 IS 1200: Part 5-1982
B
Reinforcement (Rebar) Inspection
  • Check diameter, spacing, and quantity of rebars as per structural drawings (IS 456:2000)
  • Ensure stirrups (ties) are properly spaced and adequately tied with binding wire
  • Verify lap length, anchorage, and bends as per IS 2502:1963
  • Maintain the required concrete cover (25-40mm for beams, depending on design)
  • Ensure rebars are clean, free from rust, oil, and dirt
  • Check proper curtailment of bars as per bending schedule
  • Verify provision of chair bars to maintain top reinforcement position
IS 456:2000 IS 2502:1963 IS 1786:2008
C
Beam Levels & Alignment
  • Verify that beam levels match approved structural drawings
  • Ensure beam alignment is correct, and vertical and horizontal position is maintained
  • Use a spirit level or total station to check beam straightness and level
  • Check center line of beams with respect to column centerlines
  • Verify beam-column junction details and connections
IS 456:2000
D
Concrete Mix & Material Approval
  • Ensure the approved concrete mix is used (IS 10262:2019)
  • Check that aggregates, cement, and water comply with quality standards (IS 383:2016)
  • Verify water-cement ratio and ensure no excess water is added to the mix
  • Check cement storage conditions and expiry dates
  • Verify aggregate gradation and maximum size compliance
IS 10262:2019 IS 383:2016 IS 456:2000
4

During Pouring Inspection

A
Concrete Placement & Compaction
  • Ensure slump test is performed to check workability (IS 1199:1959)
  • Pour concrete in layers (not exceeding 1.5m height) to prevent segregation
  • Use mechanical vibrators properly to remove air pockets and ensure proper compaction (IS 4925:2004)
  • Avoid over-vibration as it may lead to segregation of the mix
  • Maintain consistent pouring rate to avoid cold joints
  • Check concrete temperature during hot weather concreting
IS 1199:1959 IS 4925:2004
B
Level & Alignment Check
  • Use plumb bob or total station to ensure beams are aligned and straight
  • Check beam level matches slab and column levels to avoid misalignment
  • Monitor formwork for any movement or bulging during pouring
  • Verify beam soffit levels at multiple points
IS 456:2000
C
Quality Control During Pouring
  • Take concrete cube samples at regular intervals for strength testing
  • Monitor concrete consistency and workability throughout pouring
  • Check for any segregation or bleeding in the concrete
  • Ensure proper surface finish and leveling of beam top
  • Document any interruptions or delays during pouring
IS 516:1959 IS 456:2000
5

Post-Pouring Inspection

A
Initial Curing & Protection
  • Cover freshly poured concrete with wet hessian cloth or polythene sheets to prevent drying
  • Apply curing compound or keep concrete moist for at least 7 days (IS 7861:1981)
  • Protect from direct sunlight, rain, and wind that may affect curing
  • Maintain consistent moisture content during curing period
  • Monitor concrete temperature during initial setting period
IS 7861:1981 IS 456:2000
B
Surface Finish & Defects Check
  • Remove formwork only after achieving the required strength (as per IS 456:2000)
  • Inspect for honeycombing, cracks, or segregation in the beam surface
  • Ensure proper rectification of minor defects using grout if required
  • Check for any blow holes or surface irregularities
  • Verify beam dimensions after formwork removal
  • Document any surface defects with photographs
IS 456:2000
C
Concrete Strength Testing
  • Collect cube samples (150mm x 150mm x 150mm) for compressive strength testing (IS 516:1959)
  • Test cube samples at 7, 14, and 28 days to verify compressive strength
  • Ensure minimum characteristic strength (e.g., M20, M25) is achieved as per project requirements
  • Conduct non-destructive tests if required (Rebound hammer, UPV)
  • Document all test results with proper identification
IS 516:1959 IS 456:2000 IS 13311:2019
D
Final Handover & Documentation
  • Ensure all Inspection Reports, Cube Test Results, and Material Test Certificates are documented
  • Close any Non-Conformance Reports (NCRs) before approval
  • Get final sign-off from consultants/structural engineers
  • Prepare as-built drawings if any deviations from original design
  • Submit complete quality dossier for the beam construction
IS 456:2000
6

Column Interface Quality Check

A
Column-Beam Junction Details
  • Verify proper development length of beam reinforcement into column
  • Check column stirrup spacing in beam-column joint zone (IS 13920:2016)
  • Ensure proper confinement reinforcement in joint area
  • Verify beam top bars are properly anchored into column
  • Check for proper concrete consolidation in joint region
  • Ensure column vertical bars are not displaced during beam casting
IS 456:2000 IS 13920:2016
B
Construction Joint Treatment
  • Clean construction joints thoroughly before casting subsequent lifts
  • Apply bonding agent at construction joints if required
  • Ensure surface roughness at joints for better bond
  • Remove laitance and loose concrete from joint surfaces
  • Wet the surface before casting fresh concrete
IS 456:2000
C
Column Reinforcement Continuity
  • Verify column main bars are continuous through beam level
  • Check for proper spacing between column bars and beam reinforcement
  • Ensure adequate cover to column reinforcement
  • Verify column bar splices are as per approved drawings
  • Check column bar projection for subsequent floor construction
IS 456:2000 IS 2502:1963
7

Common Defects & Remedial Measures

Defect Possible Cause Remedial Measure
Honeycombing Inadequate compaction, high water-cement ratio Chipping and patching with polymer modified mortar
Cracks in Beam Early formwork removal, shrinkage Epoxy injection for structural cracks, monitoring
Cold Joints Delay between concrete pours Surface preparation and epoxy bonding agent
Improper Alignment Formwork movement during pouring Assessment by structural engineer, possible strengthening
Low Strength Concrete Improper mix design, poor curing Non-destructive testing, reinforcement if required
Cover Deficiency Improper spacer placement, formwork issues Local repair with protective coating
Joint Leakage Poor formwork joint sealing Grout injection and surface treatment
Reinforcement Corrosion Inadequate cover, poor concrete quality Cathodic protection, concrete repair
8

Quality Inspection Equipment

  • Measuring tape and steel scale for dimensional checks
  • Spirit level for checking horizontal and vertical alignment
  • Slump cone for concrete workability testing
  • Thermometer for concrete temperature monitoring
  • Cube molds for strength test samples
  • Magnifying glass for surface defect inspection
  • Rebound hammer for non-destructive strength testing
  • Camera for documentation and evidence
  • Cover meter for checking concrete cover
  • Ultrasonic pulse velocity equipment
  • Weighing scale for material proportioning
  • Total station for precise level and alignment checks
9

Testing Procedures for Beam Quality

Test Type Purpose IS Code Frequency
Slump Test Workability assessment IS 1199:1959 Every batch or 30m³
Compressive Strength Concrete strength verification IS 516:1959 6 cubes per 25m³ or per day
Rebound Hammer Surface hardness check IS 13311:Part 2 As required for NDT
UPV Test Homogeneity and crack detection IS 13311:Part 1 Representative sampling
Core Test In-situ strength assessment IS 516:1959 When cube strength is low
Cover Measurement Reinforcement cover check IS 456:2000 5% of reinforcement
Load Test Structural adequacy IS 456:2000 If required by engineer
10

Comprehensive Inspection Checklist - Beam Quality

Inspection Item Acceptance Criteria Reference
Formwork Dimensions ± 5mm of plan dimensions IS 14687:1999
Reinforcement Spacing Stirrups: ± 10mm, Main bars: ± 5mm IS 2502:1963
Concrete Cover 25mm for beams + 5mm tolerance IS 456:2000
Concrete Slump 100-150mm for beams IS 1199:1959
Concrete Strength Min characteristic strength + 1.65 × standard deviation IS 516:1959
Beam Alignment ± 6mm from true position IS 456:2000
Surface Finish No honeycombing, voids < 10mm IS 456:2000
Column-Beam Joint Proper confinement and development length IS 13920:2016
Formwork Removal Min 7 days or 70% strength achieved IS 456:2000
Curing Duration Minimum 7 days continuous curing IS 456:2000
11

Quality Assurance Final Checklist

  • All material test certificates are available and reviewed
  • Formwork inspection completed and approved
  • Reinforcement inspection completed as per drawings
  • Concrete mix design approved and implemented
  • Slump tests conducted and results within limits
  • Cube samples collected and tested
  • Proper compaction and vibration completed
  • Curing process implemented correctly
  • Formwork removed at appropriate time
  • Surface defects identified and rectified
  • Dimensional checks completed and within tolerance
  • Column-beam junction properly executed
  • NDT tests conducted if required
  • All NCRs closed with proper remedial action
  • Final approval from structural consultant
  • Quality dossier prepared and documented
  • As-built drawings updated with any changes
  • Handover certificate issued
12

Important Safety & Quality Notes

  • Always check and ensure conformance to project-specific requirements and drawings.
  • Maintain proper curing for minimum 7 days to achieve optimum strength.
  • Ensure all tests and inspections are documented and traceable.
  • Obtain proper approvals before proceeding to subsequent construction stages.
  • For higher seismic zones, additional reinforcement detailing may be required.
  • Hot weather concreting requires special precautions for temperature control.
  • Cold weather concreting may require protection from freezing.
  • Monitor concrete strength development before applying loads.
  • Ensure proper safety measures during formwork and reinforcement work.
  • Regular calibration of testing equipment is essential for accurate results.
Download PDF
×

Thank You!

Thanks for your feedback Karthik. We'll review your suggestions.