Roof Beam & Tie Beam Quality Check Procedure
Standard operating procedure for quality control of Plinth, Roof Beams & Tie Beams, ensuring structural stability, durability, and load-bearing capacity through proper inspection and testing methods in accordance with Indian Standards (IS Codes).
Structure Type: RCC Beams
Quality Priority: High
Validity: All Projects
To establish a comprehensive quality control procedure for Plinth, Roof Beams & Tie Beams, ensuring structural stability, durability, and load-bearing capacity through proper inspection and testing methods in accordance with Indian Standards (IS Codes).
- Ensure formwork dimensions match the structural drawing
- Formwork should be properly supported and braced to avoid deformation (IS 14687:1999)
- Ensure formwork is clean, oiled, and has no gaps to prevent leakage
- Verify that formwork can withstand pouring pressure without displacement
- Check formwork joints are tight and properly sealed
- Verify proper centering and support system for beam soffit
IS 14687:1999
IS 1200: Part 5-1982
- Check diameter, spacing, and quantity of rebars as per structural drawings (IS 456:2000)
- Ensure stirrups (ties) are properly spaced and adequately tied with binding wire
- Verify lap length, anchorage, and bends as per IS 2502:1963
- Maintain the required concrete cover (25-40mm for beams, depending on design)
- Ensure rebars are clean, free from rust, oil, and dirt
- Check proper curtailment of bars as per bending schedule
- Verify provision of chair bars to maintain top reinforcement position
IS 456:2000
IS 2502:1963
IS 1786:2008
- Verify that beam levels match approved structural drawings
- Ensure beam alignment is correct, and vertical and horizontal position is maintained
- Use a spirit level or total station to check beam straightness and level
- Check center line of beams with respect to column centerlines
- Verify beam-column junction details and connections
IS 456:2000
- Ensure the approved concrete mix is used (IS 10262:2019)
- Check that aggregates, cement, and water comply with quality standards (IS 383:2016)
- Verify water-cement ratio and ensure no excess water is added to the mix
- Check cement storage conditions and expiry dates
- Verify aggregate gradation and maximum size compliance
IS 10262:2019
IS 383:2016
IS 456:2000
- Ensure slump test is performed to check workability (IS 1199:1959)
- Pour concrete in layers (not exceeding 1.5m height) to prevent segregation
- Use mechanical vibrators properly to remove air pockets and ensure proper compaction (IS 4925:2004)
- Avoid over-vibration as it may lead to segregation of the mix
- Maintain consistent pouring rate to avoid cold joints
- Check concrete temperature during hot weather concreting
IS 1199:1959
IS 4925:2004
- Use plumb bob or total station to ensure beams are aligned and straight
- Check beam level matches slab and column levels to avoid misalignment
- Monitor formwork for any movement or bulging during pouring
- Verify beam soffit levels at multiple points
IS 456:2000
- Take concrete cube samples at regular intervals for strength testing
- Monitor concrete consistency and workability throughout pouring
- Check for any segregation or bleeding in the concrete
- Ensure proper surface finish and leveling of beam top
- Document any interruptions or delays during pouring
IS 516:1959
IS 456:2000
- Cover freshly poured concrete with wet hessian cloth or polythene sheets to prevent drying
- Apply curing compound or keep concrete moist for at least 7 days (IS 7861:1981)
- Protect from direct sunlight, rain, and wind that may affect curing
- Maintain consistent moisture content during curing period
- Monitor concrete temperature during initial setting period
IS 7861:1981
IS 456:2000
- Remove formwork only after achieving the required strength (as per IS 456:2000)
- Inspect for honeycombing, cracks, or segregation in the beam surface
- Ensure proper rectification of minor defects using grout if required
- Check for any blow holes or surface irregularities
- Verify beam dimensions after formwork removal
- Document any surface defects with photographs
IS 456:2000
- Collect cube samples (150mm x 150mm x 150mm) for compressive strength testing (IS 516:1959)
- Test cube samples at 7, 14, and 28 days to verify compressive strength
- Ensure minimum characteristic strength (e.g., M20, M25) is achieved as per project requirements
- Conduct non-destructive tests if required (Rebound hammer, UPV)
- Document all test results with proper identification
IS 516:1959
IS 456:2000
IS 13311:2019
- Ensure all Inspection Reports, Cube Test Results, and Material Test Certificates are documented
- Close any Non-Conformance Reports (NCRs) before approval
- Get final sign-off from consultants/structural engineers
- Prepare as-built drawings if any deviations from original design
- Submit complete quality dossier for the beam construction
IS 456:2000
- Verify proper development length of beam reinforcement into column
- Check column stirrup spacing in beam-column joint zone (IS 13920:2016)
- Ensure proper confinement reinforcement in joint area
- Verify beam top bars are properly anchored into column
- Check for proper concrete consolidation in joint region
- Ensure column vertical bars are not displaced during beam casting
IS 456:2000
IS 13920:2016
- Clean construction joints thoroughly before casting subsequent lifts
- Apply bonding agent at construction joints if required
- Ensure surface roughness at joints for better bond
- Remove laitance and loose concrete from joint surfaces
- Wet the surface before casting fresh concrete
IS 456:2000
- Verify column main bars are continuous through beam level
- Check for proper spacing between column bars and beam reinforcement
- Ensure adequate cover to column reinforcement
- Verify column bar splices are as per approved drawings
- Check column bar projection for subsequent floor construction
IS 456:2000
IS 2502:1963