CC Road Construction SOP

Standard Operating Procedure for Cement Concrete (CC) road construction, ensuring strength, durability, and compliance with relevant IS Codes for civil construction projects.

Duration: 14-21 days Team: 8-15 workers Risk Level: Medium

1. Purpose

To establish a structured process for the construction of Cement Concrete (CC) roads, ensuring strength, durability, and compliance with relevant IS Codes for civil construction projects.

2. Scope

This procedure applies to all CC road construction projects, covering material selection, surface preparation, concrete laying, curing, and quality control as per IS codes. It includes main access roads, internal pathways, and service corridors within construction projects.

3. Responsibilities

Project Manager

Ensures project execution as per design and safety standards

Site Engineer

Monitors work progress, verifies material quality, and ensures proper execution

Supervisor

Coordinates manpower and ensures adherence to specifications

Equipment Operators & Workers

Perform excavation, mixing, pouring, and finishing tasks

Quality Inspector

Conducts material and concrete testing to ensure compliance with IS codes

Safety Officer

Implements safety protocols to prevent site accidents

Material Manager

Ensures timely availability of quality-tested materials as per specifications

Survey Team

Establishes proper alignment, levels, and gradients for road construction

4. Materials & Equipment

Materials

Cement (OPC/PPC), Coarse Aggregates, Fine Aggregates, Water, Admixtures, Reinforcement Bars

Earthwork Equipment

Excavators & Loaders for earthwork, Compactors for subgrade preparation

Concrete Equipment

Concrete Mixer, Batching Plant, Transit Mixer, Vibrators

Paving Equipment

Slipform Paver, Manual Paving Equipment, Concrete Screeds

Leveling Equipment

Leveling Instruments, Straight Edge, Templates for surface finishing

Curing Equipment

Water Sprayers, Curing Compounds, Hessian Cloth, Plastic Sheets

Finishing Tools

Trowels, Bull Floats, Edgers, Joint Cutting Saws

Testing Equipment

Slump Cone, Cube Molds, Schmidt Hammer, Compression Testing Machine

5. Procedure

1
Pre-Work Preparation
  • Survey & Marking: Establish the road alignment and levels as per drawings
  • Subgrade Preparation:
    • - Excavate and compact the soil
    • - Perform plate load test as per IS 1888 to check soil strength
    • - Achieve minimum 97% compaction of MDD as per IS 2720
  • Sub-base Layer (if required):
    • - Place a granular sub-base (GSB) layer as per IS 2720
    • - Compact using rollers to achieve required density
    • - Check levels and crossfall (2-2.5%)
  • Material Preparation:
    • - Test cement, aggregates, and water as per IS standards
    • - Store materials safely at designated locations
    • - Prepare reinforcement if required by design
2
Subgrade and Sub-base Preparation
  • Subgrade Preparation:
    • - Excavate to the desired depth (typically 450-600mm below finished road level)
    • - Remove all organic material, debris, and unsuitable soil
    • - Proof-roll the subgrade to identify soft spots; remove and replace with suitable material
    • - Compact the subgrade to minimum 97% of Modified Proctor Density (MDD) as per IS 2720
    • - Conduct field density tests every 500 sq.m to verify compaction
    • - Check levels at 10m intervals to ensure proper gradient (transverse slope 2-2.5%)
  • Sub-base Layer:
    • - Place granular sub-base (GSB) material in layers not exceeding 150mm thickness
    • - Ensure proper moisture content (OMC ±2%) for optimum compaction
    • - Compact each layer using vibratory rollers (minimum 8-10 ton capacity)
    • - Ensure minimum compaction of 98% MDD as per IS 2720
    • - Verify levels and camber (2-2.5%) using appropriate instruments
    • - Conduct plate load tests to check the bearing capacity (min. CBR value as per design)
  • Drainage Provisions:
    • - Install side drains as per design specifications
    • - Create proper outlets for water discharge
    • - Ensure longitudinal slope of at least 1 in 500 for effective drainage
    • - Install culverts at required locations as per drainage plan
    • - Check functionality of drainage system before proceeding with concrete work
3
Concrete Placement and Finishing
  • Formwork Placement:
    • - Install formwork along road edges ensuring proper alignment
    • - Set forms to correct levels using surveying instruments
    • - Secure forms firmly using steel pins/stakes at 1m intervals
    • - Apply releasing agent to prevent concrete adhesion
    • - Verify formwork stability and dimension accuracy
  • Reinforcement (if required):
    • - Place reinforcement bars/mesh as per structural drawings
    • - Use 8mm-10mm diameter bars with spacing as per design (typically 150-200mm c/c)
    • - Ensure proper cover using spacer blocks (minimum 50mm from bottom)
    • - Check for proper binding and overlaps (minimum 50D or as specified)
    • - Install dowel bars at expansion joints if required by design
  • Concrete Mix Preparation:
    • - Use minimum M30 grade concrete as per IS 456:2000
    • - Follow approved mix design with proper proportioning
    • - Maximum water-cement ratio: 0.45
    • - Use mechanical mixers or ready-mix concrete from approved plants
    • - Test slump at batching point and placement location (target: 75-100mm)
  • Concrete Pouring:
    • - Pour concrete evenly, ensuring no segregation
    • - Maximum pouring height: 1.5m to prevent segregation
    • - Pour in panels as per planned construction joints
    • - Complete each panel in one continuous operation
    • - Maintain consistent supply of concrete to avoid cold joints
  • Vibration & Compaction:
    • - Use vibratory screeds for surface compaction
    • - Use needle vibrators at 500mm intervals for internal compaction
    • - Insert vibrator vertically at close intervals (300-600mm)
    • - Maintain vibration duration of 15-30 seconds per point
    • - Ensure a dense, uniform surface without honeycombing
  • Finishing:
    • - Use a bull float immediately after screeding
    • - Wait for bleed water to evaporate before further finishing
    • - Use wood floats followed by steel trowels for smoother finish
    • - Create required texture (broom finish for skid resistance)
    • - Check surface regularity with 3m straight edge (max deviation 3mm)
4
Curing & Expansion Joints
  • Initial Curing:
    • - Apply curing compound or cover with wet burlap immediately after finishing
    • - Protect concrete from rain, wind, and direct sunlight
    • - Avoid any traffic for first 24 hours
  • Main Curing Process:
    • - Cover with hessian cloth and sprinkle water for at least 14 days
    • - Maintain moisture consistently (never let concrete dry)
    • - Use curing compounds if water curing is not feasible
    • - Minimum curing period: 14 days for OPC, 21 days for PPC/PSC
  • Contraction Joints:
    • - Create joints within 24 hours using concrete saw (1/4 depth of slab)
    • - Typical spacing: 4.5m to 5m as per IRC:58
    • - Follow specified joint pattern from drawings
  • Expansion Joints:
    • - Provide expansion joints at regular intervals as per IS 6509
    • - Install dowel bars coated with bond-breaker if required
    • - Maintain 20-25mm gap filled with bitumen/filler board
  • Joint Sealing:
    • - Clean joints thoroughly before applying sealant
    • - Fill joints with appropriate sealant material (polysulphide/polyurethane)
    • - Ensure sealant is flush with surface or slightly recessed
5
Final Inspection and Testing
  • Surface Inspection:
    • - Check for cracks, honeycombing, or surface defects
    • - Verify surface regularity using 3m straight edge (max 3mm deviation)
    • - Ensure proper camber and cross slopes for drainage
  • Strength Testing:
    • - Test concrete cubes at 7 and 28 days
    • - Conduct core tests if required
    • - Verify achievement of design strength (min. M30 grade)
  • Joint Inspection:
    • - Check all joints for proper execution and sealing
    • - Verify joint width and depth as per specifications
    • - Ensure no unsealed joints remain
  • Drainage Check:
    • - Conduct water test to verify proper drainage
    • - Ensure no water ponding on finished surface
    • - Verify side drains functionality
  • Road Opening:
    • - Allow vehicle traffic only after achieving 80% of design strength
    • - Typically after 14-21 days depending on cement type
    • - Install any required signage or road markings

6. Quality Checks and Tests

Compressive Strength Test

As per IS 516:1959 to verify concrete strength (28-day strength ≥ 30 MPa)

Slump Test

As per IS 1199:1959 to check workability (75-100mm for road concrete)

Density Tests

For subgrade and sub-base layers to verify minimum 97% MDD

Level & Alignment Checks

Maximum deviation: ±10mm longitudinal, ±5mm cross-section

Material Quality Tests

Aggregate testing for gradation, shape, strength, and cleanliness

Surface Regularity

Maximum 3mm deviation under 3m straight edge

Temperature Monitoring

Concrete placement temperature 5°C to 35°C, monitoring during curing

Water-Cement Ratio

Maintain W/C ratio ≤ 0.45 for durability and strength

7. Safety Measures

PPE Compliance

Helmets, gloves, safety boots, and high-visibility vests mandatory for all personnel

Traffic Management

Use barricades and signage for public safety and proper traffic diversion

Electrical Safety

Ensure proper grounding of all electrical equipment and ELCB protection

Heavy Equipment Safety

Only trained operators with valid licenses to operate machinery

Concrete Handling

Use protective gloves and clothing to prevent cement burns and dermatitis

Eye Protection

Mandatory safety goggles during mixing, pouring, and cutting operations

First Aid

Maintain first aid station on site with eye wash facility and trained personnel

Heat Stress Prevention

Regular hydration breaks and shade provision during hot weather

8. Troubleshooting Common Issues

Plastic Shrinkage Cracks

Problem: Fine cracks appearing on surface during setting.

Solution: Apply fog spray/evaporation retarder, use windbreaks, schedule pours during cooler times, and begin curing immediately after finishing. Consider adding polypropylene fibers to the mix.

Surface Scaling

Problem: Flaking or peeling of surface.

Solution: Ensure proper air entrainment, avoid excess water in the mix, use proper finishing techniques (no finishing while bleed water is present), and provide adequate curing period with consistent moisture.

Poor Concrete Strength

Problem: Test cubes failing to meet target strength.

Solution: Check cement quality, verify W/C ratio, ensure proper gradation of aggregates, improve mixing time/technique, and verify curing conditions. If detected early, consider longer curing; if structural, conduct core tests for further evaluation.

Joint Spalling

Problem: Edge damage along joints.

Solution: Create joints at proper timing, ensure joint sawing depth is correct (1/4 of slab depth), use proper joint filler materials, avoid heavy loads on new pavement, and ensure proper concrete consolidation at joints.

9. Documentation and Approval

Maintain material test reports and mix design approvals
Record compaction and strength test results in site registers
Document daily progress, curing period, and quality control checks
Maintain photographic evidence of key construction stages
Obtain final approval from quality engineers before opening the road for use
Prepare as-built drawings showing actual construction details
Compile complete road history file for future maintenance reference

10. References and Standards

IS 456:2000 - Plain and reinforced concrete code of practice
IS 10262:2019 - Concrete mix proportioning guidelines
IS 516:1959 - Method of tests for strength of concrete
IS 1199:1959 - Methods of sampling and analysis of concrete
IS 2386 (Parts 1-8) - Methods of test for aggregates for concrete
IS 383:2016 - Specification for coarse and fine aggregates
IRC:15-2017 - Code of practice for construction of concrete roads
IRC:58-2015 - Guidelines for the design of plain jointed rigid pavements

11. Pro Tips

Weather Considerations

Avoid concrete pouring during extreme temperatures or heavy rainfall; ideal temperature range: 15-25°C

Camber Design

Ensure proper camber (1:50 to 1:60) for effective drainage and prevent water ponding

Vibration Technique

Vibrate concrete in systematic pattern to avoid over or under-vibration (15-30 seconds per point)

Joint Timing

Cut contraction joints within 4-12 hours of concrete placement depending on setting time

Curing Efficiency

Consider automated sprinkler systems for large projects to ensure consistent moisture

Hot Weather Concreting

Use chilled water, ice, or set-retarding admixtures to control setting time in hot weather

Trial Mix Testing

Always conduct site trials of concrete mix before full-scale production

Team Experience

Use experienced finishing crews for better surface quality and reduced rework

12. Conclusion

By following this Standard Operating Procedure, CC road construction can be executed efficiently, ensuring strength, durability, and compliance with IS codes. Proper execution and strict adherence to safety measures will result in long-lasting and low-maintenance roads. Regular quality checks and documentation will help maintain the highest standards throughout the construction process, resulting in durable infrastructure that withstands the test of time and provides reliable service throughout the project's operational life.

Download PDF