WBM Road

Standard Operating Procedure for Water Bound Macadam (WBM) road construction, ensuring structural stability, durability, and compliance with industry standards and IS Codes.

Duration: 7-14 days Team: 5-8 workers Risk Level: Medium

1. Purpose

To outline the standard procedure for Water Bound Macadam (WBM) road construction, ensuring structural stability, durability, and compliance with industry standards and IS Codes for facilitating effective site access and movement of personnel, materials, and equipment.

2. Scope

This SOP applies to all WBM road construction activities within solar project sites, including material selection, surface preparation, laying, compaction, quality control, and testing as per relevant IS codes. It covers internal roads, perimeter roads, and access roads that comprise the transportation network for the project.

3. Responsibilities

Project Manager

Ensures adherence to project specifications, IS codes, and completion within timelines

Site Engineer

Monitors execution, verifies compliance with drawings, and ensures quality standards

Supervisor

Manages labor, ensures tools and materials availability, and oversees workflow

Operators & Workers

Execute material spreading, rolling, and compaction with proper technique

Quality Inspector

Conducts quality checks on materials, thickness, and compaction density as per IS standards

Safety Officer

Implements safety protocols and ensures safe working conditions throughout construction

Material Manager

Ensures timely availability of quality-tested materials as per specifications

Survey Team

Establishes proper alignment, levels, and gradients for road construction

4. Materials & Equipment

Coarse Aggregates

Stone metal, gravel, or crushed stone (IS 383:2016) with specified gradation

Screenings

Stone dust or gravel as per IS 2386 with proper size distribution

Binding Material

Stone dust, soil, or sand (IS 6579) with suitable plasticity index

Water

Clean, potable water for compaction (IS 456:2000), free from impurities

Earthmoving Equipment

Excavator, loader, motor grader for preparation and leveling

Transport Vehicles

Dumpers, tippers for material transport to site

Compaction Equipment

10-12 ton vibratory/static rollers, hand rammers for edges

Water Tanker

For controlled water application during construction

Measuring Tools

Total station, levels, boning rods, tapes, templates, camber boards

Testing Equipment

Core cutter, sand replacement apparatus, sieves, moisture meters

5. Procedure

1
Pre-Work Preparation
  • Review approved road design, drawings, and specifications
  • Verify the road alignment and cross-section with reference benchmarks
  • Check availability of all required materials, equipment, and testing tools
  • Conduct soil investigation to determine subgrade properties
  • Prepare detailed execution plan with material requirements
  • Ensure availability of water source for construction
  • Set up material testing area and establish quality control procedures
2
Subgrade Preparation
  • Clear vegetation, remove topsoil and debris from the road corridor
  • Excavate and remove loose material from subgrade to required depth
  • Fill depressions with suitable material and compact to uniform density
  • Compact the subgrade using rollers to achieve minimum 98% of MDD
  • Shape the subgrade to required camber (2-3% cross slope)
  • Ensure side drains are properly excavated for water drainage
  • Conduct subgrade testing as per IS 2720 to verify compaction
  • Install level markers at 10m intervals to guide thickness control
3
Sub-Base Preparation
  • Lay granular sub-base material in uniform thickness (100-150mm)
  • Spread material to required width and cross-section
  • Apply water uniformly to achieve optimum moisture content (OMC)
  • Roll and compact with vibratory roller starting from edges to center
  • Ensure minimum 8 passes of roller for proper compaction
  • Check levels and transverse profile at 20m intervals
  • Verify sub-base compaction to minimum 97% MDD as per IS 2720
  • Allow curing for 24 hours before proceeding to next layer
4
WBM Base Course (First Layer)
  • Check coarse aggregate for proper gradation (63-45mm for 1st layer)
  • Set string lines and level pegs to control thickness (75-100mm)
  • Place aggregate spreader boxes at required intervals
  • Spread coarse aggregates uniformly to desired thickness plus 25%
  • Hand-pack larger stones along edges for reinforcement
  • Roll dry aggregates with 3-5 passes of static roller
  • Apply water uniformly using pressure distributor
  • Continue rolling while sprinkling water until aggregate is well-keyed
  • Spread screenings (Type B as per IS 383) gradually during rolling
  • Apply binding material in thin layers (if required by specification)
  • Continue rolling with simultaneous brooming to fill voids
  • Apply water and roll until slurry is formed to fill voids completely
  • Check surface with 3m straight edge for depressions (max 12mm allowed)
  • Allow layer to set and dry before proceeding to next layer
5
WBM Intermediate Layer (Second Layer)
  • Verify finished first layer meets required tolerance and hardness
  • Check coarse aggregate for proper gradation (53-22.4mm for 2nd layer)
  • Repeat spreading, watering, and rolling processes as in first layer
  • Apply smaller screenings (Type B/C as per IS 383) for better interlocking
  • Continue rolling and brooming until layer is thoroughly compacted
  • Check and correct surface irregularities continuously
  • Verify 2nd layer compaction with field density tests
  • Allow compacted layer to set and dry before proceeding
6
WBM Wearing Course (Final Layer)
  • Verify intermediate layer compliance with specifications
  • Use smaller aggregate size (40-20mm) for final layer
  • Spread material to final road profile including camber (2.5%)
  • Roll and compact as per previous layers with additional passes
  • Use Type D screenings (11.2-0.6mm) for final filling of voids
  • Apply binding material if specified, ensuring it doesn't form cake
  • Final 2-3 passes with roller without vibration for smooth finish
  • Check entire surface with 3m straight edge (max 8mm deviation allowed)
  • Ensure proper cross drainage works meet with road edges
  • Allow completed road to cure for minimum 72 hours before opening
7
Road Shoulder Construction
  • Excavate and prepare shoulder area parallel to main carriageway
  • Fill shoulder with specified material (usually granular/earthen)
  • Compact shoulder material in layers not exceeding 150mm thickness
  • Ensure shoulder has slight outward slope (4-5%) for drainage
  • Verify shoulder edge is 25-50mm below finished road surface
  • Compact junction between road edge and shoulder thoroughly
  • Install drainage elements (side drains) as per drawings

6. Quality Control Measures

Material Testing

Sieve analysis, impact value, abrasion test as per IS 2386

Compaction Tests

Field density test using core cutter/sand replacement method

Thickness Check

Test pits at 500m intervals to verify layer thickness

Surface Evenness

Maximum 8mm deviation under 3m straight edge

Moisture Content

Maintain OMC ±2% during compaction as per IS 2720

Camber & Grade

2.5% cross slope and longitudinal grade as per design

Load Bearing

Plate load test as per IS 9214 at critical locations

Documentation

Maintain test records, daily progress, and non-conformance reports

7. Safety Measures

Personal Protection

Mandatory PPE including helmets, high-visibility vests, and safety boots

Traffic Management

Proper barricading, signage, and flagmen where applicable

Equipment Safety

Trained operators, reverse horns, and clear communication protocols

Dust Control

Regular water sprinkling to minimize airborne dust

First Aid

First aid kits and trained personnel available on site

Electrical Safety

Protection for underground utilities and overhead lines

Access Control

Designated paths for workers and equipment to avoid accidents

Tool Safety

Regular inspection and proper storage of hand tools

8. Troubleshooting Common Issues

Surface Waviness

Problem: Uneven surface after compaction with roller marks.

Solution: Use lighter roller initially, maintain uniform moisture, check roller speed, and scarify affected areas for reworking if required. Ensure proper gradation of materials.

Poor Interlocking

Problem: Aggregate not properly keying together, leading to loose surface.

Solution: Apply appropriate screenings, maintain optimum moisture, increase roller passes, and ensure proper grading of materials. Check aggregate quality (avoid rounded particles).

Segregation of Aggregates

Problem: Separation of coarse and fine materials during spreading.

Solution: Minimize handling and height of dumping, use proper spreading techniques, mix materials properly before spreading, and avoid excessive watering before compaction.

Edge Failures

Problem: Crumbling or settlement at road edges.

Solution: Provide proper shoulder support, hand-pack larger stones at edges, extend rolling 300mm beyond edge, and ensure proper drainage away from edges.

9. References and Standards

IS 383:2016 - Specification for coarse and fine aggregates from natural sources
IS 2386 - Methods of test for aggregates for concrete
IS 2720 - Methods of test for soils (various parts for different tests)
IRC:19-2005 - Standard Specifications and Code of Practice for Water Bound Macadam
MORTH Specifications for Road and Bridge Works (Section 400)
IS 9214 - Method of determination of modulus of subgrade reaction (K value) of soils
IS 456:2000 - Plain and reinforced concrete - Code of practice
IS 516 - Method of tests for strength of concrete

10. Best Practices and Tips

Weather Consideration

Avoid WBM work during heavy rain or extreme temperatures

Layer Thickness

Maintain uniform thickness with template controls throughout

Water Application

Use controlled spraying to avoid flooding or washing away fines

Rolling Technique

Start from edges and progress toward center with specified overlap

Material Storage

Stack materials on hard, clean surface with proper segregation

Level Monitoring

Use fixed reference points and frequent level checks during construction

Traffic Management

Plan construction in half-width where existing traffic must be maintained

Drainage Provision

Ensure cross drainage works are completed before road construction

11. Conclusion

By following this Standard Operating Procedure, WBM road construction can be executed efficiently, with high quality, and structural durability. Proper execution ensures roads that provide reliable access throughout the solar project site while maintaining compliance with all relevant standards. This SOP should be reviewed periodically and updated based on field experiences and changes in regulations.